03 — R&D · greenhouse technology

R&D at KUBO

Internship and part-time job at the R&D department of greenhouse builder KUBO. I didn't have one fixed project but helped out on several. Below are the three I spent the most time on: an airflow test, redesigning a tool, and a heat test on PVC strips.

ContextInternship → part-time
WhereKUBO Group, Monster
Year2025
TeamR&D department
The end of the 85 metre test hose in the hall
Fig. 1 — The end of the 85 m test hoseKUBO

Measuring the airflow of an AHU

01
Test setup · data

KUBO's Ultra Clima system has an Air Handling Unit (AHU) for each path in the greenhouse: a heating and cooling block with a fan that blows air through a long hose. Growers want to know how much air goes into the greenhouse (Q), because that tells them how quickly all the air gets replaced.

This was the biggest project of my internship. We set up one AHU with an 85 m hose and ran the fan at different speeds. Q can be calculated in a few ways, so we measured several things to compare them afterwards.

The measurements showed how the pressure is spread along the hose. With the results we could adjust the pattern of holes in the hose, so the air comes out more evenly along its length.

My role
  • Building the setup
  • Running the tests
  • Processing the data
  • Improving the setup
Fig. 2 — The test setup, simplified Select a measuring point
85 m coil fan hose air A 1 2 3 4

Fig. 3 — Static pressure along the hose, per fan speed
Average–
Lowest–
Highest–

Approximate, read from my report.

The AHU test setup in the hall: coil block, fan and hose
Fig. 4 — The AHU in the test hall

Redesigning a tool

02
Redesign → production

At a greenhouse near the coast in Portugal, the salty air made the aluminium corrode. The corrosion pushed on the glass until the panes broke. As a temporary fix, the frame around the glass was opened up a little with a special tool: you place it on the profile, tighten a bolt, and it pulls part of the profile up.

There was one tool, but three more were needed. The 3D models were lost and the people who made the original no longer worked there. At first I was only asked to get some quotes, but it turned into a redesign that I mostly did on my own.

Fig. 5 — The tool, step by step

Heat test on PVC strips

03
Research · heat test

For a project in Saudi Arabia, another department asked whether the PVC and aluminium parts would cause problems in that climate. In a brainstorm we named three risks: UV, high temperatures and thermal expansion.

Together with a colleague I looked at heat. We built a small setup with the PVC strips that hold the glass, put it in an oven at different temperatures, and checked flexibility and deformation afterwards. At high temperatures it lost strength and shape quickly. The conclusion of the whole research: standard PVC won't hold up in that climate, but a more UV-resistant type of PVC did fine.

My role
  • Brainstorm
  • Test plan
  • Running the test
  • Reporting

Fig. 6 — The test setup with PVC strips, and in the oven

What I learned

04
  • Testing takes longer than planned

    We had a detailed test plan for the airflow test, but still had to change the setup and redo parts several times. You can't predict everything, that's why you test. Now I plan extra time for it.

  • Prototypes for problems, too

    Normally I build a prototype to test a design. The oven test was only to understand a risk better, which was new to me.